Details: Copies of documents, such as − but not limited to – Construction Notice to Proceed, Construction Status Reports, contractor reporting forms, work orders, project directories, and the like that specify subcontractors and other salient points (noted below) for construction or renovation projects valued at $2,000,000 or more. Please include information for both currently active projects as well as those completed since September 1, 2020 at the following campuses:
University of Connecticut, Storrs ▪ University of Connecticut, Hartford ▪ University of Connecticut Health Center
We do not need every document that mentions subcontractors, just one for each subcontractor or set of subcontractors. Specifically, we seek:
• Project Name
• Project number
• Projected completion date
• Prime/General Contractor name(s)
• Construction Manager (at Risk) name
• Architect/Engineer names
• Subcontractor names
Excel spreadsheets containing similar information are welcome.